Overall Objective:
Raise $5 million in capital and $1 million in
endowments in order to
break ground for the new Shelter in the spring of 2006.
Phase I: April 2004 – April 2005, “Quiet Phase”, Before the
Public Announcement
(Achieve at least 50% of goal by 12/04, 70% - 80% by
5/05)
2004:
-
Established infrastructure – committees,
marketing materials, letters of recommendation, grant boilerplate,
financials, Stray Cat Strut Planning
-
Determined sponsorship levels and prospects
-
Confirmed architect requirements
-
June – December
-
Initiate donor cultivation and solicitation
-
Initiate Grant applications and follow-up
-
Advisory Board meeting (October)
-
Stray Cat Strut – design, mold, artists,
and sponsors
-
Building – Pre-design Planning (November
2004 – April 2005) and Ecological Site Planning (November 2004 – June
2005)
2005:
-
January – April:
-
Continue donor cultivation and solicitation
-
Continue grant processes
-
Stray Cat Strut – cats completed and
mounted
-
Advisory Board event (April)
-
Building – Professional Consultation
(January – April) and Architectural Consultation (initiate in January),
Energy Analysis and Modeling and Material Analysis (March - September)
Second Phase:
May 2005 – April 2006, General Public Solicitation
(Achieve at least 95% of goal by 12/05)
-
May:
-
Stray Cat Strut – Launch Memorial Day
Parade 2005 (cats
back and mounted on bases with placques)
-
Announcement of Public Campaign using
Stray Cat
Strut in Dearborn Memorial Day Parade
-
Initiate special gifts campaign
-
June – September:
-
Stray Cat Strut – Cats on display at Sponsors
for Dearborn’s Art on the Avenue. Cats
travel to prearranged placement for further media coverage and public awareness.
Suggestions/thoughts: Greenfield
Village, HFC Library, Ford World Headquarters, Fairlane Town Center, HFCC
-
Continue donor cultivation and solicitations
-
Continue grant processes
-
Building - contractor evaulation, furnishings
selection
-
October – December:
-
Stray Cat Strut – Auction event (October)
-
Announcement (October) and sale of community
participation opportunities
-
Continue donor cultivation and solicitations
-
Continue grant processes
2006:
Third Phase:
April – December 2006, Community Gifts, Cleanup, Construction (8
months)
-
April - December
-
Ground breaking celebration (April)
-
Initiate construction
-
Continue grant processes
-
Continue donor cultivation and solicitations
-
Complete construction (December)
Fourth Phase:
January 2007, Move In !
|